Mojave
Client
Comfort Inn / Electrify America
Location
Mojave, USA
Year
2019

Molle Energy worked with Edison to install a new power pole service. We used horizontal directional drilling (Boring) to pull a new primary conduit over 200’ to an open trench where multiple duct banks parallel.
A new PME, Capacitor Pad, and Transformer make up the Edison Infrastructure required to install a 1600A Switchgear which sits 3 feet above grade in this flood zone.